Tewkesbury Garden Communities Progress Update
Our charter for promoting good growth.
Executive Summary
Executive Summary: Tewkesbury Garden Communities 2024 Annual Report
This year has been marked by significant achievements and forward momentum. As Chief Executive of Tewkesbury Borough Council but also the Senior Reporting Officer for the Garden Communities, I’m pleased to present the 2024 Annual Report
In June 2024, we celebrated the first formal signings of the Garden Communities Charter, setting a strong foundation for our future. Public consultations saw major development proposals launched by the North Ashchurch Consortium and Newland Homes, aiming to bring forward approximately 3,785 new homes between them. Additionally, applications have been submitted for the MOD land near Aston Cross and a site near Pammington, which are scheduled to deliver a further 535 homes.
The new Labour government has shown a determination to build more homes, committing to building 1.5 million within this parliament. They have also launched the New Towns Taskforce and are planning a major overhaul of the planning system and updates to the National Planning Policy Framework (NPPF).
In October 2024, our county council highways colleagues held the first public engagement activities for the proposed offline A46 solution and new M5 motorway junction. This project is designed to reduce traffic congestion, support future housing and employment land delivery, and enhance the strategic connectivity of the A46 to the north-east.
Following the recommendations of the 2023 Cratus report, we overhauled our governance and engagement arrangements and implemented a robust programme and project management system with clear timelines and deliverables.
Looking ahead, we have submitted a further stage of the bid to the Ministry of Housing, Communities and Local Government (MHCLG) for funding to establish the most appropriate delivery vehicle. We propose a locally led development corporation (LLDC), with an interim vehicle initially providing additional resources and expertise to support delivery, particularly in unlocking key infrastructure and creating an employment site.
Additionally, a funding award from Homes England will support an update to the design and construction methods of the bridge, and subsequent to Network Rail agreement, a planning application as part of the wider housing development proposal can be submitted.
This summary encapsulates the progress and strategic direction of the Tewkesbury Garden Communities programme, highlighting our commitment to sustainable development and community engagement.
Alastair CunninghamChief Executive of Tewkesbury Borough Council and Senior Responsible Officer for the Garden Communities programme
Foreword
As we reflect on the achievements of 2024 and look forward to the opportunities and challenges ahead in 2025 and beyond, I am pleased with the progress of the Tewkesbury Garden Communities programme. This annual report highlights the significant strides we have made in delivering high-quality, affordable homes that adhere to the principles of the Garden Communities Charter.
The independent review conducted in 2023 provided invaluable insights and recommendations, all of which are being addressed and most are highlighted in this report. Our commitment to these findings underscores our dedication to creating sustainable, well-planned communities that enhance the quality of life for all residents.
The review emphasized the importance of a coordinated approach to development, mitigating the risks of piecemeal or poor development. This aligns with our commitment to delivering high-quality, affordable homes that meet the principles of the Garden Communities Charter. One of the key recommendations was to create an identity for the “garden town” as it was then. That it should have its own identity and not be treated as an extension of Tewkesbury town. We very soon created the new identity of “Tewkesbury Garden Communities” – a series of connected communities with a shared supporting infrastructure.
In 2024, our team has worked tirelessly to ensure that our approach to development is both strategic and coordinated. We firmly believe that a well-planned, cohesive strategy is far superior to the fragmented, piecemeal applications that can arise from an uncoordinated planning process. This method not only preserves the integrity of our communities but also ensures that we can meet the growing demand for affordable housing without compromising on quality or sustainability.
Looking ahead to 2025 and beyond, we remain steadfast in our mission to deliver homes that are not only affordable but also exemplify the highest standards of design and environmental stewardship. Our vision is to create vibrant, inclusive communities where residents can thrive and we are committed to working collaboratively with all stakeholders to achieve this goal.
I extend my heartfelt thanks to the entire team for their dedication and hard work over the past year. Together, we will continue to build a brighter, more sustainable future for the Tewkesbury Garden Communities.
Richard StanleyLeader of Tewkesbury Borough Council
The story so far
Reflecting on five years of progress
In 2018, Tewkesbury Borough Council responded to the Ministry for Housing, Communities and Local Government’s (MHCLG) Garden Communities prospectus by submitting a bid for ‘Garden Town’ status for the proposed large-scale development east of the M5 at Tewkesbury/Ashchurch.
In 2019 a award for £8.1million was granted for the design and construction of a new bridge over the railway to unlock the land north of the MOD base for housing development and also to facilitate closure of the level crossing at Northway.
2021 unveiled an Evolution to the original concept masterplan. The plan which brought forward a suite of guiding development principles aimed to deliver 10,195 new homes supported by 100 hectares of employment land and related infrastructure over 30 years.
In 2023, an appeal and subsequent Judicial Review of the bridge planning application was upheld in relation to the wider scheme and environmental impact assessment implying that the planning application was quashed. Subsequently, the delay to the overall delivery schedule meant project construction funding was withdrawn.
In April 2023, Cratus Consulting began a review of the programme, resulting in 17 recommendations to enhance management and delivery. These recommendations were endorsed by the council in July 2023 and have since been implemented.
This progress update not only explains the delivery of those recommendations but also highlights the positive steps taken and future plans for the Tewkesbury Garden Communities programme.
A significant change in 2023 was the shift from a single large-scale Garden Town plan to a more distributed ‘garden communities’ approach, now known as the Tewkesbury Garden Communities development. A charter outlining key development principles was developed with stakeholder input and published in March 2024. It has since been endorsed by developers and community groups, serving as a guiding agreement for all parties involved.
In May 2023, local elections resulted in Tewkesbury Borough Council having no overall political control, comprising 16 Liberal Democrats, nine Conservatives, four Green Party members, seven Independents, and two from the Isbourne & Winchcombe Independents group. This political shift, along with the new programme approach and charter, has fostered broad cross-party support for the Tewkesbury Garden Communities programme.
Cratus report recommendation 1:
Publish a clear and tangible timeline
The opportunity
Making the case for Tewkesbury Garden Communities
The UK is facing a housing crisis, with issues of both availability and affordability, and the Tewkesbury area is no exception. The Ashchurch location, both north and south of the current A46, presents an excellent opportunity for large-scale, integrated development. This area accepting the highway capacity issue, benefits from relatively few constraints, has the potential for excellent transport links due to its proximity to the M5 and the main Birmingham to Bristol rail line, and strong potential for developing sustainable and active travel options to local employment and major sites in and around Cheltenham and Gloucester.
Key benefits:
- Housing and infrastructure: Major housing delivery in this location is crucial for securing government support for necessary infrastructure improvements. The proposed ‘offline’ solution for the A46, including an additional motorway junction south of the existing junction 9, is essential to support the strategic east-west highway corridor and bringing forward housing and strategic employment land in this area could be the incentive needed for government investment.
- Economic growth: This location also offers the potential to develop a major new business campus for Gloucestershire, which could include a skills and innovation centre focused on the Advanced Engineering and Manufacturing sector. Whilst providing employment for a sustainable development, this would attract inward investment, address critical skills shortages, and provide the business support infrastructure needed for growth and innovation.
- Job Creation and GDP Growth: The proposed 100 hectares of employment land could create up to 14,000 jobs equivalent to over £600 million of GDP growth.
- Community and regeneration: This development can act as a catalyst for major investment and regeneration in Tewkesbury town itself, boosting the sporting, leisure and cultural infrastructure of the town and local area.
Cratus report recommendation 17
Create a new storybook that brings together all the benefits and outcomes
Engagement and communications
Post the Cratus review in summer 2023 there was a major emphasis on improving engagement and communications with communities and key stakeholders.
With this focus in place between summer 2023 and spring 2024, and following feedback from stakeholders and participants, a governance review was initiated in Spring 2024.
An updated governance and engagement structure (see fig 1.) has since been developed and was formally endorsed by the council in September 2024. The structure has been operating since October 2024, with a regular schedule of meetings for all the different groups and boards now well established.
Given the long timeframe for delivery of the Garden Communities, it is essential that young people’s views are considered in respect of lifestyle expectations, design aspirations, transport preferences and housing mix and tenures – as they will eventually be the people living in the new communities. An interactive workshop was held at Tewkesbury Academy in March 2024. It saw students craft their design ideas into models showing their vision for future residential areas with a mix of leisure and retail spaces and more.
Young Gloucestershire have also been commissioned to undertake a programme of youth engagement activity with the objective of establishing a youth liaison panel which will start to operate in 2025.
In order to support the ongoing engagement and communications needs of the Garden Communities Programme and the wider Place agenda for the council there is now a dedicated Communications and Engagement Officer (Place) in position, Gethin Evans, who took up the role in April 2024.
Following this appointment, a new council Communications Strategy was approved, which specifies the Garden Communities programme as a priority communications campaign. A refresh of our website has been conducted, resulting in a more intuitive layout and more accessible information. Several consultation events have been supported by the Garden Communities team, with frequent representations at community events and expert information presented to both our parish and community liaison groups.
Cratus report recommendation 14
Develop a clear communications strategy for the Garden Communities
Current development pipeline
There are already a number of consented planning applications within the Garden Communities area, with some homes already occupied in the southern area referred to by the developer as Fiddington Fields.
Below is a summary of the major schemes either consented or currently in the planning system at various stages.
Fig. 1.a – North of A46
| Promoter/Builder | Status | Ref | Qty of homes |
|---|---|---|---|
| North Ashchurch Consortium | Pre-app | N/A | 2800* |
| MOD St Modwen | Pre-app | N/A | 350 |
| Newland Homes | Pre-app | N/A | 450 |
*The North Ashchurch Consortium masterplan for the whole northern area indicates c4350 in total. See fig 2. below. This application will also include a detailed application for the proposed new rail bridge.
Fig 1.b – South of A46
| Promoter/Builder | Status | Ref | Qty of homes |
|---|---|---|---|
| Persimmon (Fiddington 1) | Consented | 17/00520/OUT | 850 |
| Barratt (Fiddington 2) | Consented | 21/00451/OUT | 460 |
| Robert Hitchins (Fiddington 3) | Consented | 22/01320/OUT | 120 |
| Robert Hitchins (Fiddington 4) | Pre-app | N/A | 140 |
| Homedowns (Fiddington 5) | Consented | 23/00930/OUT | 30 |
| Greystoke Land (Pamington Lane) | Validated | 23/01170/OUT | 175 |
| Tinpenny Farm | Validated | 24/00639/OUT | 30 |
In addition there are a number of other major landowners currently expressing interest in bringing forward land for development in the southern area.
It is worth noting that currently the majority of the land in the Garden Communities designated area has no formal planning status, however as a consequence of a current undersupply of homes (relative to government-set targets) in the borough, significant ‘windfall’ development (i.e. planning consents which are not within a local plan) is an ongoing reality.
Fig 2. North Ashchurch Consortium concept masterplan

Northway Railway Bridge
A new rail crossing north of the A46 has always been viewed as a key item of unlocking infrastructure for the northern area of the garden communities. As a result, the borough council recently entered into a conditional sale agreement to purchase land at Northway Court Farm to facilitate bridge delivery, subject to three conditions: a)planning permission is granted for the bridge (being submitted as part of the wider outline application for the northern area), b) that the council secures sufficient funding for construction and c) any other required land parcels are acquired.
Having taken account of the appeal decision to the judicial review in relation to the previous application, the council will not be submitting a planning application to deliver a ‘standalone’ bridge. The responsibility of securing planning permission now lies with the North Ashchurch Consortium as part of their planning application for the broader scheme. An application is expected in 2025.
In December 2024, Homes England granted £89,500 to complete design work on the bridge. This work will also assess the look of the bridge and is planned for completion in spring 2025.
Fig 3. showing the extent of Flood zones and the location of the Ashchurch Bridge within the Garden Communities area. Also included is an illustration of the proposed A46 and J9a.

M5 J9/A46 Offline Solution
A major public (non-statutory) consultation exercise was held by Gloucestershire County Council (GCC) Highways from 7th Oct 2024 to 3rd Dec 2024 to introduce a number of proposed route options for an ‘offline’ A46 route and new motorway junction that would alleviate many of the current problems experienced on the A46 running through Ashchurch and connecting to the M5 motorway at junction 9. The A46 is part of the strategic road network connecting the South West to the North East of England and the East Coast ports.
An offline route would provide a number of benefits, including:-
- Ensure the Strategic Road Network meets likely future development needs in the Ashchurch area considering potential for long-term growth
- Improve local journey times and reliability during peak periods at M5 Junction 9 and on the existing A46 corridor between M5 Junction 9 and Teddington Hands roundabout
- Improve the overall performance of the A46 strategic corridor between the M5 to the south and the A46 to the north of Evesham, ensuring the route provides a reliable connection between the Midlands and South-West England
- Improve safety performance at M5 Junction 9 and the A46 between M5 Junction 9 and Aston Cross for all users
- Reduce severance and improve the experience for walking and cycling journeys at M5 Junction 9 and along/across the A438 and A46 between Tewkesbury School and Aston Cross
Fig 4. Route options for A46 offline

The scheme has completed the Strategic Outline Business Case stage and whilst further business case stages and related approvals are necessary, the schedule indicates construction in the early 2030’s.
If the scheme is approved to go forward to develop a full outline business case, GCC will lead on the development of the outline case through to submission.
Cratus report recommendation 5 and 6
Appoint a Programme Officer and develop a work programme
English Devolution and Local Government Reorganisation
In their white paper published in December 2024, the Government set out a compulsory move from two-tier authority areas (where around 40% of the English population live) to unitary authorities. There is no option to opt-out of this, but local councils (both district and county) are required to create their own proposals for how best to proceed.
At the time of going to press, there are two leading proposals: 1. to create a single unitary merging all six district within Gloucestershire with the county council; 2. is to create two unitaries, broadly East and West with Tewkesbury and Cheltenham boroughs joining Cotswold District leaving Gloucester City, Forest of Dean and Stroud Districts to form the other.
For all the latest news and wider information on English Devolution and Local Government Reorganisation, click here.
Stewardship
Initial meetings have taken place with both Ashchurch Rural (11 Nov) and Northway (11 Dec) parishes to introduce the concept of stewardship at scale for the TGC.
Stewardship in the context of Garden Communities primarily means the long term (notionally in perpetuity) management and care of community assets created through development. Typically this will include (non-adopted) green open spaces, sports and play facilities and community buildings.
It can also include elements of community building and placemaking where the established stewardship organisation is actively involved in community engagement and ‘animation’, organising events, provision of local services (e.g. on-demand local transport), delivering well-being programmes and can stretch as far as supplying utilities and data services and potentially running commercial activities within the community, e.g. cinemas, arts centres, cafes, pubs etc.
The team have been actively engaging with Homes England and external advisors on how to establish appropriate and sustainable stewardship arrangements over the long term. This included a visit to the Chichester Community Development Trust in November. This will be a significant workstream in 2025 and we have received some initial funding from Homes England to support the initial development of a stewardship strategy.
Cratus report recommendation 15
Create an integrated stakeholder and community engagement plan
Delivery Vehicle
In September 2024 the council authorised an update to the earlier submission of a bid to MHCLG for funding and support to establish the most effective delivery vehicle to continue the delivery the Tewkesbury Garden Communities. An interim vehicle (IV) is proposed as a preliminary stage prior to establishing a Locally Led Development Corporation (LLDC) which in would requiring an act of parliament will take time to put in-place. The IV would provide an appropriate and robust legal structure and would bring additional resources from central government to support the ongoing delivery especially that of the employment. It would also potentially provide capital funds for some land acquisition including that of the employment site.
A decision from MHCLG is expected in early 2025.
Cratus report recommendation 3
Take a ‘back-to-basics’ approach to the business case for a development corporation.
What next? Expectations/Plans for 2025
The key priorities for the Garden Communities programme for 2025 are as follows:-
- Host a major public engagement event early in 2025 to share progress on the garden communities development with the community.
- Secure additional funding to further develop plans for long term stewardship within the Garden Communities area and establish a local stewardship company
- Commission (jointly with Homes England) a sustainable movement strategy for the Garden Communities.
- Agree the full scope and commission (subject to funding) a Strategic Framework Masterplan for the southern area (i.e. south of the A46) of the garden communities development.
- Subject to government funding and full council approval, establish an ‘interim vehicle’ to lead on the development and infrastructure delivery.
- Secure funding and planning approval to build the new rail bridge and access road at Northway.
- Continue to promote the Garden Communities Charter and encourage developers to sign-up to it.
- Develop an Employment, Skills and Innovation delivery strategy for the Garden Communities area.
- Continue to support the County Council promoted M5 J9a/A46 offline solution.
- Continue to work with Homes England to secure strategic land acquisitions and ensure high quality placemaking is planned.
- Continue to work with all landowners and/or developers to bring forward their applications through the Local Planning Authority.
There are a number of significant government initiatives and activities that will also impact the garden communities programme in 2025, including:
- The New Towns Taskforce
- Revisions to the National Planning Policy Framework (NPPF).
- The commitment to deliver 1.5million homes during this parliament.
- The English Devolution White Paper and the move to a unitary authority.
2025 promises to be a very significant year for the GC programme and we look forward to updating you on the progress made in 12 months time!
The Tewkesbury Garden Communities Programme Team
December, 2024
Cratus report recommendation 1
Publish a clear and tangible timeline for the development
Alastair CunninghamChief Executive of Tewkesbury Borough Council and Senior Responsible Officer for the Garden Communities programme
Richard StanleyLeader of Tewkesbury Borough Council